Anglian Water held two webinars on 18 and 19 Jan for Councils and the Community Working Group respectively. Two points on programme were:

Expected to publish a report on the previous consultation last week – this has not happened by Tuesday 31st Jan

As confirmed by the Planning Inspectorate (PINS) today; they have submitted their final proposal documents on 31 Jan and there will now be a 28 day period while the Inspector considers whether to accept the application. If so the opportunity to register as an Interested Party and publication of the documents would then take place. AW said in the webinar they had 220 docs ready for ready for submission.

Furthermore, AW reported some technical discussions with other agencies and possibly land owners will continue.

They reported at the webinar they received only 286 feedback forms amongst other forms of “engagement”. This is probably a sign of respondent fatigue compared to previous consultations.

It did not appear at the webinar that the majority of the points raised by FDPC had resulted in any design changes since the last CWG meeting although they confirmed the beneficial changes within Fen Ditton Parish boundary they have introduced since the last Consultation. These were the relocation of a tunnel construction site to be slightly further away from Red House Cottage and the removal of a permanent vent shaft at that site which means there would be no requirement for permanent access to that site. The bund remains at 5m height but lighting masts will be 5m high with downward lit area.

It is important that Fen Ditton PC registers with the Planning Inspectorate as a Interested Party in order to have the choice to submit representations to the Inspector in the examination period. I am happy to do this in my name unless anyone else volunteers. All residents should be encouraged to also register if they wish.

In the meantime, I have registered to receive emailed updates from PINS. Anyone can do this at: